Dandong Waste Treatment Plant Reconstruction and Construction (Incineration Power Generation) PPP Project, with daily treatment of 1500 tons of domestic waste, will be constructed in two phases, and the first phase will be configured with 2 × 500t/d waste incinerator grate+22MW steam turbine generator unit; Reserve land for Phase II construction, and configure a 500t/d waste incinerator grate+9MW steam turbine generator unit; The garbage storage pit shall be built at one time, and the annual operation time shall not be less than 333 days; The newly built fly ash landfill with a storage capacity of 151200 cubic meters has a service life of 14 years; The existing domestic waste landfill is closed, with an area of about 140000 square meters.
Solution: Rolls Fire Emergency Lighting and Evacuation Indication System